On November 2, 2006 it is intended to arrange ceremonies related with putting the Water Purifiers into operation in Kurdamir region Karrar village and Ujar region Bargushad communities. 
The ceremony will be arranged within "Improvement of Potable Water Provision” project implemented by "Umid” Humanitarian and Social Support Center, Karrar village and Bargushad communities under financial support of Baku/Tbilisi/Ceyhan (BTC Co.) and South Caucasian Pipelines (SCP Co.) Partners.

Water used by Karrar village inhabitants will be purified and given to the population in pure form through a modern water purifier installed by an executive agency AquaZone, the winner of the bid and whereas the inhabitants of Bargushad village will benefit by the water purified through a water purifier installed by executive agency Aquatech – the another bid winner.

Total amount of the project implemented by Karrar village is 23 874 AZN, the community contribution being 4193 AZN. Purchase of the facilities took 8129 AZN out of the total amount, whereas construction works were conducted with the remaining 11 552 AZN out of the total amount. 
Bargushad community’s project total amount comprises 34 417 AZN including a community contribution at amount of 6396 AZN. Another spending out of the total amount was related with purchase of the equipment which comprised 12000 AZN. Construction works involved 16 021 AZN – the remaining funds out of the total.

Quality of the water purified through water purifiers was analyzed by MediClub Company, the purified water is in compliance with norms according to findings of the Company.

"Aran-K” and "Gulshad-B” Limited Liability Societies registered in a relevant unit of the Ministry of Justice will be responsible for further management of and ensuring the sustainability exploitation of installed Water Purifiers.